Project: Cedar Hollow Family Health Clinic, two-story, 24,000 SF, Cedar Hollow, MN Bids due: August 21, 2026, 2:00 p.m.
Addenda
- Addendum 1 (August 3): revised partition schedule on A-601. No change to 09A scope.
- Addendum 2 (August 10): adds Level 5 finish at the two-story lobby.
09A includes
- Non-structural metal stud framing
- Gypsum board, tape and finish to Level 4
- Level 5 finish at the two-story lobby (Addendum 2)
- Shaft wall at elevator and mechanical shafts
- Sound attenuation batts in partitions noted on A-601
- In-wall blocking for casework and wall-mounted equipment
- Exterior glass-mat gypsum sheathing
- Firestopping at rated penetrations made by this trade